A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?
1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 20:00
The blank button automatically displays next to the data when you select a range of numeric data which is an available option for creating a chart
Answers: 3
question
Computers and Technology, 23.06.2019 07:00
1. you have a small business that is divided into 3 departments: accounting, sales, and administration. these departments have the following number of devices (computers, printers, etc.): accounting-31, sales-28, and administration-13. using a class c private network, subnet the network so that each department will have their own subnet. you must show/explain how you arrived at your conclusion and also show the following: all available device addresses for each department, the broadcast address for each department, and the network address for each department. also, determine how many "wasted" (not usable) addresses resulted from your subnetting (enumerate them).
Answers: 3
question
Computers and Technology, 23.06.2019 14:30
The basic work area of the computer is it screen that you when you first fire up your computer
Answers: 1
question
Computers and Technology, 23.06.2019 17:00
1. which of the following is not an example of an objective question? a. multiple choice. b. essay. c. true/false. d. matching 2. why is it important to recognize the key word in the essay question? a. it will provide the answer to the essay. b. it will show you a friend's answer. c. it will provide you time to look for the answer. d. it will guide you on which kind of answer is required.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 23.07.2019 08:30
question
Mathematics, 23.07.2019 08:30
Questions on the website: 13722361