A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 21:00
It is not a good idea in a cover letter to mention another person whom the employer knows.
Answers: 1
question
Computers and Technology, 23.06.2019 13:00
Which one of the following voltages should never be measured directly with a vom? a. 1200 v b. 500 v c. 800 v d. 100v
Answers: 2
question
Computers and Technology, 23.06.2019 17:00
What are the 12 colors of the spectrum called?
Answers: 1
question
Computers and Technology, 24.06.2019 12:00
How can we take picture in this app
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 06.05.2020 00:28
Questions on the website: 13722363