A project consists of 8 activities. The activity completion times and the precedence relationships are as follows:
Activity. Completion time Days. immediate predecessor activities.
A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F
1. Draw the network diagram using AON model notations:
2. What is the critical path?
3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.
4. What is the minimum time to complete the projects?
Please answer and thank you
Answers: 1
Computers and Technology, 23.06.2019 08:00
Which argument is not a valid filter? does not equal this quarter filter by cell color all of these are valid filter arguments.
Answers: 2
Computers and Technology, 24.06.2019 10:10
Which view in a presentation program displays a split window showing the slide in the upper half and a blank space in the lower half?
Answers: 1
Computers and Technology, 24.06.2019 12:00
What is a sketch or blueprint of a web page that shows the structure (but not the detailed design) of basic page elements such as the logo, navigation, content, and footer?
Answers: 3
Computers and Technology, 24.06.2019 15:30
Emma is using an artificial intelligence system, which contains information on botany, to identify a type of plant from an image. what type of ai is emma using?
Answers: 1
A project consists of 8 activities. The activity completion times and the precedence relationships a...
History, 18.10.2019 14:30
Chemistry, 18.10.2019 14:30
History, 18.10.2019 14:30
Mathematics, 18.10.2019 14:30
Mathematics, 18.10.2019 14:30
Spanish, 18.10.2019 14:30
Mathematics, 18.10.2019 14:30
Mathematics, 18.10.2019 14:30
World Languages, 18.10.2019 14:30
Chemistry, 18.10.2019 14:30
Social Studies, 18.10.2019 14:30