A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 08:00
Which argument is not a valid filter? does not equal this quarter filter by cell color all of these are valid filter arguments.
Answers: 2
question
Computers and Technology, 24.06.2019 10:10
Which view in a presentation program displays a split window showing the slide in the upper half and a blank space in the lower half?
Answers: 1
question
Computers and Technology, 24.06.2019 12:00
What is a sketch or blueprint of a web page that shows the structure (but not the detailed design) of basic page elements such as the logo, navigation, content, and footer?
Answers: 3
question
Computers and Technology, 24.06.2019 15:30
Emma is using an artificial intelligence system, which contains information on botany, to identify a type of plant from an image. what type of ai is emma using?
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
History, 18.10.2019 14:30
question
Mathematics, 18.10.2019 14:30
question
Social Studies, 18.10.2019 14:30
Questions on the website: 13722362