You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 02:30
If you turn on the lock alpha button , what happens
Answers: 1
question
Computers and Technology, 23.06.2019 08:00
The managing director of a company sends a christmas greeting to all his employees through the company email. which type of network does he use? he uses an .
Answers: 3
question
Computers and Technology, 23.06.2019 16:10
What is the ooh? a. omaha occupation handbook b. online occupational c. occupations online d. occupational outlook handbook select the best answer from the choices provided
Answers: 3
question
Computers and Technology, 23.06.2019 19:00
Acompany is hiring professionals for web designing. the firm is small with few resources. they want employees who possess problem-solving skills and can independently carry out responsibilities. which kind of employee should they select?
Answers: 2
You know the right answer?
You have just used the network planning model for a county road resurfacing project and found the cr...
Questions
question
History, 10.05.2021 16:00
question
Mathematics, 10.05.2021 16:00
Questions on the website: 13722362