subject

When computing a forward pass you carry the early finish to the next activity where it becomes the early start unless the succeeding activity is a merge activity. In this case you select the largest early finish number of all the immediate predecessor activities. Why do you select the largest early finish number

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 08:00
Apex q: what does a low employment rate indicate? a. not many people are earning high salaries b. not many people are going to college c. not many people are renting their homes d. not many people have jobs
Answers: 2
question
Computers and Technology, 22.06.2019 09:50
Assume that you have an sorted array of records. assume that the length of the array (n) is known. give two different methods to search for a specific value in this array. you can use english or pseudo-code for your algorithm. what is the time complexity for each algorithm and why?
Answers: 1
question
Computers and Technology, 22.06.2019 15:20
The north and south regions had very diferent economies in the 1800s.
Answers: 1
question
Computers and Technology, 23.06.2019 04:31
Cloud computing service providers manage different computing resources based on the services they offer. which resources do iaas and paas providers not manage? iaas providers do not manage the for the client, whereas paas providers usually do not manage the for their clients. iaas- storage server operating system network paas- applications interafce storage vertualiation
Answers: 2
You know the right answer?
When computing a forward pass you carry the early finish to the next activity where it becomes the e...
Questions
question
Mathematics, 30.11.2020 17:40
Questions on the website: 13722366