Ann is invited to help an Agile Release Train (ART) that has struggled through multiple Innovation and Planning (IP) Iterations. They just finished the second Iteration in the Program Increment (PI) and have nothing to demonstrate at the System Demo. Program stakeholders are really concerned.
What should Ann do?

a. Have every team demonstrate their team increment to the stakeholder separately in the team branch
b. Re-architect the system so that there are no dependencies between the teams, and integration is not needed
c. Stop working on any new functionality and fully integrate and trust the system, adjust scope based on learning
d. Re-plan the current PI. De-Scope to leave enough time to integrate what has been built during the IP iteration

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 18:00
Which if the following allows you to view and access important information about your documents all in one location
Answers: 3
question
Computers and Technology, 22.06.2019 01:40
Kali, a python programmer, is using the turtle module to write the word “hello.” which code should she use to indicate the location to begin writing the word? a # pick up the turtle and move it to its starting location. b penup(-100, 200) goto() pendown() c penup() goto(-100, 200) pendown() d # pick up the turtle and move it to (-100, 200)
Answers: 2
question
Computers and Technology, 22.06.2019 17:30
Under which key category do the page up and page down keys fall? page up and page down keys fall under the keys category.
Answers: 1
question
Computers and Technology, 24.06.2019 00:00
Visualizing a game of “tag” to remember the meaning of contagious
Answers: 3
You know the right answer?
Ann is invited to help an Agile Release Train (ART) that has struggled through multiple Innovation a...
Questions
question
Mathematics, 11.12.2019 10:31
Questions on the website: 13722362