An over-target baseline (otb) is a comprehensive rebaselining effort that is best categorized as an internal replanning effort.

a. true
b. false

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 08:00
What best describes a career pathway in a lodging career? a worker starts out as an amusement attendant, then becomes a recreation worker, and then becomes a gaming worker within five years. a worker starts out as a bell hop, then becomes a night clerk, and then becomes a hotel manager within five years. a worker starting out as a tour guide, then becomes a travel clerk, and then becomes a travel agent within five years. a worker starts out as a server, then becomes a food preparer, and then becomes a head chef within five years.
Answers: 1
question
Computers and Technology, 23.06.2019 09:30
After you present a proposal, the committee starts asking you questions, some beyond the strict focus of your proposal. they ask questions about implications in other fields and knowledge about other fields. you are asked to redo your proposal. what is most likely missing? breadth of material depth of material clarity of material details of material
Answers: 1
question
Computers and Technology, 24.06.2019 14:30
Ahousehold consists of a married couple and their twin five-year old daughters. the couples children had no income and lived with their parents all of last year. how many exemptions can the couple claim on last years tax return or they file with the “ married filing jointly “ status? a. 4 b. 5 c. 3 d. 2
Answers: 1
question
Computers and Technology, 24.06.2019 14:40
Create a function (prob3_6) that will do the following: input a positive scalar integer x. if x is odd, multiply it by 3 and add 1. if the given x is even, divide it by 2. repeat this rule on the new value until you get 1, if ever. your program will output how many operations it had to perform to get to 1 and the largest number along the way. for example, start with the number 3: because 3 is odd, we multiply by 3 and add 1 giving us 10. 10 is even so we divide it by 2, giving us 5. 5 is odd so we multiply by 3 and add one, giving us 16. we divide 16 (even) by two giving 8. we divide 8 (even) by two giving 4. we divide 4 (even) by two giving 2. we divide 2 (even) by 2 to give us 1. once we have one, we stop. this example took seven operations to get to one. the largest number we had along the way was 16. every value of n that anyone has ever checked eventually leads to 1, but it is an open mathematical problem (known as the collatz conjectureopens in new tab) whether every value of n eventually leads to 1. your program should include a while loop and an if-statement.
Answers: 3
You know the right answer?
An over-target baseline (otb) is a comprehensive rebaselining effort that is best categorized as an...
Questions
question
German, 13.05.2021 22:10
question
Mathematics, 13.05.2021 22:10
Questions on the website: 13722361