What is the critical path?
a. the path from resource to task that passes through all critical components of a project plan
b. the path between tasks to the projects finish that passes through all critical components of a project plan
c. the path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
d. the path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 06:30
What result from the passage of this amendment
Answers: 1
question
Computers and Technology, 22.06.2019 06:30
Requirement types discussed during software development include functional and color scheme nonfunctional and code style constraint and nonfunctional fashionable and functional.
Answers: 2
question
Computers and Technology, 24.06.2019 01:30
How can you make your column headings stand out?
Answers: 1
question
Computers and Technology, 24.06.2019 03:30
What is the purpose of a computer network needs assessment? to analyze which workers need more training to improve their performance to compare worker productivity to determine what steps employees can take to increase company revenue to evaluate how to move from the current status to the desired goal
Answers: 2
You know the right answer?
What is the critical path?
a. the path from resource to task that passes through all critica...
Questions
question
Spanish, 17.05.2021 23:00
question
Mathematics, 17.05.2021 23:00
question
Mathematics, 17.05.2021 23:00
question
Mathematics, 17.05.2021 23:00
question
Mathematics, 17.05.2021 23:00
Questions on the website: 13722360