The material requirements plan (mrp) uses which of the following to calculate requirements?
= bill of material, payroll schedule, and capacity plan
=master production schedule and capacity plan
= inventory data, production strategy, and supplier list
= master production schedule, bill of material, and inventory data

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 04:30
Dr. wisteria is a prominent chiropractor in the chicago area. she wants to provide a forum for her patients to discuss their health concerns and to seek and offer advice to other patients. which telecommunications tool is most appropriate for dr. wisteria's needs?
Answers: 3
question
Computers and Technology, 22.06.2019 17:40
Gabe wants to move text from one document to another document. he should copy the text, paste the text, and open the new document highlight the text, select the cut command, move to the new document, make sure the cursor is in the correct location, and select the paste command select the save as command, navigate to the new document, and click save highlight the text, open the new document, and press ctrl and v
Answers: 1
question
Computers and Technology, 23.06.2019 06:00
Which statistical function in a spreadsheet you to see how far each number varies, on average, from the average value of the list?
Answers: 2
question
Computers and Technology, 23.06.2019 11:50
While preforming before operation pmcs, you notice the front right tire appears slightly under-inflated. what is the proper action?
Answers: 3
You know the right answer?
The material requirements plan (mrp) uses which of the following to calculate requirements?
=...
Questions
question
Physics, 15.02.2021 15:30
question
English, 15.02.2021 15:30
question
History, 15.02.2021 15:30
question
Chemistry, 15.02.2021 15:40
Questions on the website: 13722367