Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s)
A 4 -
B 5 -
C 6 A, B
D 4 B
E 10 C
F 8 C, D

Assume the project completion time is 19 weeks. Please find out ES, EF, LF, LS and total slack time for each activity. Please also identify the critical path.

(Note: you can create a table in the excel as below. Once you are done, copy the table to the space provided here).

Activity ES EF LS LF TS
A
B
C
D
E
F

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:00
Ok, so, theoretical question: if i bought the mona lisa legally, would anyone be able to stop me from eating it? why or why not?
Answers: 1
question
Business, 22.06.2019 03:40
Apharmaceutical packaging company (ppc) has decided to reorganize its processes into cells. the company has four different production operations, each requiring a unique piece of equipment. the names and functions of the four pieces of equipment are sort, count, place, and package. the company packages five different families of products (a, b, c, d, and e). the tables below indicate the demand (total units/day by product family), required operations, and operation cycle times for each product family. assume that any individual piece of equipment is available to operate 16 hours/day, but 2 hours (in total) are lost each day on each piece of equipment due to breaks and meetings when operators are not available to operate the equipment. how many minutes/day are available for production
Answers: 3
question
Business, 22.06.2019 04:50
Steffi is reviewing various licenses and their uses. match the licenses to their respective uses. you are eligible to work within the state. you are eligible to sell limited investment securities. you are eligible to sell fixed income investment products. your compensation is fee based. section 6 section 7 section 63 section 65
Answers: 3
question
Business, 22.06.2019 12:50
Performance bicycle company makes steel and titanium handle bars for bicycles. it requires approximately 1 hour of labor to make one handle bar of either type. during the most recent accounting period, barr company made 7,700 steel bars and 2,300 titanium bars. setup costs amounted to $35,000. one batch of each type of bar was run each month. if a single company-wide overhead rate based on direct labor hours is used to allocate overhead costs to the two products, the amount of setup cost assigned to the steel bars will be:
Answers: 2
You know the right answer?
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine....
Questions
question
Mathematics, 16.12.2020 19:40
question
Biology, 16.12.2020 19:40
question
English, 16.12.2020 19:40
Questions on the website: 13722367