Wilson Co. purchased land as a factory site for $900,000. Wilson paid $80,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,800,000. An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000.
The cost of the land that should be recorded by Wilson Co. is:
a. $980,480
b. $986,880
c. $989,880
d. $996,280
Answers: 1
Business, 21.06.2019 14:30
If tracking employees through technology is not illegal, why should megan be concerned if she is not involved in any misconduct?
Answers: 1
Business, 22.06.2019 18:30
What historical context does wiesel convey using the allusion of a fiery sky? he compares the sky to hell. the fires from air raids during world war ii the cremation of jews in the concentration camps the outbreak of forest fires from bombs in world war ii
Answers: 1
Business, 23.06.2019 01:30
Young owners of a sole proprietorship will likely not find financial support available from?
Answers: 2
Business, 23.06.2019 02:00
Heyak believed that the economy could be hard to measure because
Answers: 2
Wilson Co. purchased land as a factory site for $900,000. Wilson paid $80,000 to tear down two build...
Mathematics, 26.08.2019 13:30
History, 26.08.2019 13:30
Biology, 26.08.2019 13:30
Mathematics, 26.08.2019 13:30
Mathematics, 26.08.2019 13:30
Physics, 26.08.2019 13:30
Mathematics, 26.08.2019 13:30
Biology, 26.08.2019 13:30
Mathematics, 26.08.2019 13:30
Mathematics, 26.08.2019 13:30
Biology, 26.08.2019 13:30
History, 26.08.2019 13:30