You are managing a project that has the following activities: - Activity A can start immediately and has an estimated duration of eight weeks.
- Activity B can also start immediately and has an estimated duration of seven weeks.
- Activity C can start after Activity A is completed and has an estimated duration of one week.
- Activity D can start after Activity B is completed and has an estimated duration of six weeks.
- Activity E can start after both Activities C and D are completed and has an estimated duration of seven weeks.
- Activity F can start after Activity D is completed and has an estimated duration of two weeks.
Your sponsor is very disappointed that the project is taking longer than he expected and asked you to shorten the project duration by at least two weeks. You decided to shorten Activity A first as it is not a very critical activity in the project and has the longest duration. What will be the impact of your decision?
a. It will create a new critical path.
b. It will shorten the duration of the project.
c. The project duration will be eighteen weeks now.
d. It will not shorten the duration of the project.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 15:30
Josie, an unmarried taxpayer, has $155,000 in salary, $10,000 in income from a passive investment in a limited partnership, and a $26,000 passive loss from a real estate rental activity in which she actively participates. if her modified adjusted gross income is $155,000, how much of the $26,000 loss is deductible
Answers: 1
question
Business, 22.06.2019 00:50
Cool beans is a locally owned coffee shop that competes with two large coffee chains, planeteuro and frothies. alicia, the owner, hired two students to count the number of customers that entered each of the coffee shops to estimate what percent of people who are interested in coffee are visiting each shop. after a week, the students found the following results: 589 visited cool beans, 839 visited planeteuro, and 1,290 visited frothies. the students were surprised that cool beans had 139 visits on monday which represented 59% of all people who visited one of the three coffee shops on mondays. how many people visited one of the three coffee shops during the week?
Answers: 2
question
Business, 22.06.2019 17:20
States that if there is no specific employment contract saying otherwise, the employer or employee may end an employment relationship at any time, regardless of cause. rule of fair treatment due-process policy rule of law employment flexibility employment at will
Answers: 1
question
Business, 22.06.2019 18:10
Why would an investor invest in your stocks
Answers: 1
You know the right answer?
You are managing a project that has the following activities: - Activity A can start immediately a...
Questions
question
English, 12.03.2021 16:00
question
Mathematics, 12.03.2021 16:00
question
Mathematics, 12.03.2021 16:10
Questions on the website: 13722367