The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-seat stadium. The construction starts on Monday, February 15, 2016andmustbe completed within 52 weeks. A penalty clause of $15,000 per week for each full or partial of delay beyond this date was written into the contract. Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300,000on the project. He was confident that the project could be completed on time with an allowance made for the usual delays anticipated in such a large project. Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 27. Past experience indicated a fifty–fifty chance of a strike. Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that such a strike would last either eight weeks (70 percent chance) or possibly 12 weeks (30 percent chance). Jim was not pleased with these prospects. However, before he had a chance to discuss contingency plans he was interrupted by Jack White, the vice-president for engineering. Jack commented that a colder December than had been assumed was now being predicted. This factor had not been taken into consideration during earlier estimates since previous forecasts called for milder weather. Concrete pouring in December might thus require in one out of every three cases (depending on the temperature) special heating that costs $500 per week. This additional information did not please Jim at all. The chances for delay were mounting. And an overhead expense of $500 per week would be incurred in case of any delay that exceeds the baseline schedule as defined in Appendix. The technical details of the project are given in the appendix to this case. The management team was asked to consider alternatives for coping with the situation. At the end of the week, four proposals were submitted:

Required:
a. Expedite the pouring of seat gallery supports. This would cost $20,000 and cut the duration of the activity to six weeks.
b. Put a double shift on the filling of the field. A cost of $10,000 would result in a five-week time reduction.
c. The roof is very important since it precedes several activities. The use of three shifts and some overtime could cut six weeks off the roofing at an additional cost of only $9,000.
d. Do nothingAppendix: Technical Details of the StadiumThe stadium is an indoor structure with a seating capacity of 20,000.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:30
The cost of capital: introduction the cost of capital: introduction companies issue bonds, preferred stock, and common equity to aise capital to invest in capital budgeting projects. capital is』necessary factor of production and like any other factor, it has a cost. this cost is equal to the select the applicable security. the rates of return that investors require on bonds, preferred stocks, and common equity represent the costs of those securities to the firm. companies estimate the required returns on their securities, calculate a weighted average of the costs of their different types of capital, and use this average cost for capital budgeting purposes. required return on rate: when calculating om operations when the firm's primary financial objective is to select shareholder value. to do this, companies invest in projects that earnselect their cost of capital. so, the cost of capital is often referred to as the -select -select and accruals, which a se spontaneously we hted average cost of capital wa c our concern is with capital that must be provided by select- 쑤 interest-bearing debt preferred stock and common equity. capital budgeting projects are undertaken, are not included as part of total invested capital because they do not come directly from investors. which of the following would be included in the caculation of total invested capital? choose the response that is most correct a. notes payable b. taxes payable c retained earnings d. responses a and c would be included in the calculation of total invested capital. e. none of the above would be included in the cakulation of total invested capital.
Answers: 2
question
Business, 22.06.2019 07:20
Suppose that real interest rates increase across europe. this development will u.s. net capital outflow at all u.s. real interest rates. this causes the loanable funds to because net capital outflow is a component of that curve.
Answers: 1
question
Business, 22.06.2019 10:30
You meet that special person and get married. amazingly your spouse has exactly the same income you do 47,810. if your tax status is now married filing jointly what is your tax liability
Answers: 2
question
Business, 22.06.2019 11:20
Stock a has a beta of 1.2 and a standard deviation of 20%. stock b has a beta of 0.8 and a standard deviation of 25%. portfolio p has $200,000 consisting of $100,000 invested in stock a and $100,000 in stock b. which of the following statements is correct? (assume that the stocks are in equilibrium.) (a) stock b has a higher required rate of return than stock a. (b) portfolio p has a standard deviation of 22.5%. (c) portfolio p has a beta equal to 1.0. (d) more information is needed to determine the portfolio's beta. (e) stock a's returns are less highly correlated with the returns on most other stocks than are b's returns.
Answers: 3
You know the right answer?
The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-sea...
Questions
question
Mathematics, 21.01.2021 17:50
question
Mathematics, 21.01.2021 17:50
Questions on the website: 13722367