Culver Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2021. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. The appropriate information related to this change is as follows: Pretax Income from:
Percentage-of-Completion Completed-Contract Difference
2014 $752,200 $586,700 $165,500
2015 683,500 444,700 238,800

Required:
a. Assuming that the tax rate is 30%, what is the amount of net income that would be reported in 2015?
b. What entry(ies) are necessary to adjust the accounting records for the change in accounting principle?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 02:20
Larissa has also provided the following information. during the year, the company raised $36 million in new long-term debt and retired $20.52 million in long-term debt. the company also sold $22 million in new stock and repurchased $32.4 million. the company purchased $54 million in fixed assets, and sold $6,107,400 in fixed assets. larissa has asked dan to prepare the financial statement of cash flows and the accounting statement of cash flows. she has also asked you to answer the following questions: 1. how would you describe east coast yachts' cash flows? 2. which cash flows statement more accurately describes the cash flows at the company? 3. in light of your previous answers, comment on larissa's expansion plans.
Answers: 2
question
Business, 22.06.2019 06:40
At april 1, 2019, the food and drug administration is in the process of investigating allegations of false marketing claims by hulkly muscle supplements. the fda has not yet proposed a penalty assessment. hulkly’s fiscal year ends on december 31, 2018. the company’s financial statements are issued in april 2019. required: for each of the following scenarios, determine the appropriate way to report the situation. 1. management feels an assessment is reasonably possible, and if an assessment is made an unfavorable settlement of $13 million is reasonably possible. 2. management feels an assessment is reasonably possible, and if an assessment is made an unfavorable settlement of $13 million is probable. 3. management feels an assessment is probable, and if an assessment is made an unfavorable settlement of $13 million is reasonably possible. 4. management feels an assessment is probable, and if an assessment is made an unfavorable settlement of $13 million is probable.
Answers: 1
question
Business, 22.06.2019 08:30
In risk management, what does risk control include? a. risk identification b. risk analysis c. risk prioritization d. risk management planning e. risk elimination need this answer now : (
Answers: 3
question
Business, 22.06.2019 13:40
Salge inc. bases its manufacturing overhead budget on budgeted direct labor-hours. the variable overhead rate is $8.10 per direct labor-hour. the company's budgeted fixed manufacturing overhead is $74,730 per month, which includes depreciation of $20,670. all other fixed manufacturing overhead costs represent current cash flows. the direct labor budget indicates that 5,300 direct labor-hours will be required in september. the company recomputes its predetermined overhead rate every month. the predetermined overhead rate for september should be:
Answers: 3
You know the right answer?
Culver Construction Company changed from the completed-contract to the percentage-of-completion meth...
Questions
question
Mathematics, 08.10.2020 02:01
Questions on the website: 13722367