Suppose a project was originally estimated to cost $100,000 and as of a given date the EV is $80,000 and the CPI is 0.80. What is the forecast cost to complete the project

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
Agood for which demand increases as income rises is and a good for which demand increases as income falls is
Answers: 1
question
Business, 22.06.2019 13:10
A4-year project has an annual operating cash flow of $59,000. at the beginning of the project, $5,000 in net working capital was required, which will be recovered at the end of the project. the firm also spent $23,900 on equipment to start the project. this equipment will have a book value of $5,260 at the end of the project, but can be sold for $6,120. the tax rate is 35 percent. what is the year 4 cash flow?
Answers: 2
question
Business, 22.06.2019 17:10
Calculate riverside’s financial ratios for 2014. assume that riverside had $1,000,000 in lease payments and $1,400,000 in debt principal repayments in 2014. (hint: use the book discussion to identify the applicable ratios.)
Answers: 3
question
Business, 22.06.2019 20:40
Cherokee inc. is a merchandiser that provided the following information: amount number of units sold 20,000 selling price per unit $ 30 variable selling expense per unit $ 4 variable administrative expense per unit $ 2 total fixed selling expense $ 40,000 total fixed administrative expense $ 30,000 beginning merchandise inventory $ 24,000 ending merchandise inventory $ 44,000 merchandise purchases $ 180,000 required: 1. prepare a traditional income statement. 2. prepare a contribution format income statement.
Answers: 2
You know the right answer?
Suppose a project was originally estimated to cost $100,000 and as of a given date the EV is $80,000...
Questions
question
Mathematics, 02.12.2020 14:00
Questions on the website: 13722367