The project deadline is the end of the year. The project consists of two activities. Activity A has a duration of two months and activity B has a duration of three months. Activities A and B can be performed concurrently. The start date for the project is set for the beginning of July. What is the maximum duration of the project

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:00
Ok, so, theoretical question: if i bought the mona lisa legally, would anyone be able to stop me from eating it? why or why not?
Answers: 1
question
Business, 22.06.2019 15:00
Portia grant is an employee who is paid monthly. for the month of january of the current year, she earned a total of $8,388. the fica tax for social security is 6.2% of the first $118,500 earned each calendar year and the fica tax rate for medicare is 1.45% of all earnings. the futa tax rate of 0.6% and the suta tax rate of 5.4% are applied to the first $7,000 of an employee's pay. the amount of federal income tax withheld from her earnings was $1,391.77. what is the total amount of taxes withheld from the portia's earnings?
Answers: 2
question
Business, 22.06.2019 15:40
Aprice control is: question 1 options: a)a tax on the sale of a good that controls the market price.b)an upper limit on the quantity of some good that can be bought or sold.c)a legal restriction on how high or low a price in a market may go.d)control of the price of a good by the firm that produces it.
Answers: 1
question
Business, 22.06.2019 16:00
In macroeconomics, to study the aggregate means to study blank
Answers: 1
You know the right answer?
The project deadline is the end of the year. The project consists of two activities. Activity A has...
Questions
question
English, 03.02.2021 20:30
question
Mathematics, 03.02.2021 20:30
question
Biology, 03.02.2021 20:30
Questions on the website: 13722363