The processing times of four jobs are given as follows: Job Processing time (minutes)
A 10
B 24
C 16
D 20
Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time order?
a. 38
b. 70
c. 152
d. 18

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:30
What is the most important factor that affects the value of a company? a) cash flow b) earnings c) supply and demand d) number of employees
Answers: 1
question
Business, 21.06.2019 20:30
Which of the following best describes the purpose of raising and lowering the required reserve ratio? a. to make sure that government spending does not result in either a surplus or deficit. b. to stimulate economic growth by making it less expensive for producers to get loans. c. to manage the economy by increasing or decreasing the amount of loans being made. d. to regulate the activity of private banks to assure an equitable distribution of wealth. 2b2t
Answers: 3
question
Business, 22.06.2019 06:20
About time delivery co. incurred the following costs related to trucks and vans used in operating its delivery service: classify each of the costs as a capital expenditure or a revenue expenditure. 1. changed the oil and greased the joints of all the trucks and vans. 2. changed the radiator fluid on a truck that had been in service for the past four years. 3. installed a hydraulic lift to a van. 4. installed security systems on four of the newer trucks. 5. overhaul the engine on one of the trucks purchased three years ago. 6. rebuilt the transmission on one of the vans that had been driven 40,000 miles. the van was no longer under warranty. 7. removed a two-way radio from one of the trucks and installed a new radio with a greater range of communication. 8. repaired a flat tire on one of the vans. 9. replaced a truck's suspension system with a new suspension system that allows for the delivery of heavier loads. 10. tinted the back and side windows of one of the vans to discourage theft of contents.
Answers: 1
question
Business, 22.06.2019 17:00
Can someone me ? i’ll mark the best answer brainliest : )
Answers: 1
You know the right answer?
The processing times of four jobs are given as follows: Job Processing time (minutes)
A 10
Questions
question
Mathematics, 18.07.2019 06:30
Questions on the website: 13722362