A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first? a. The activity with the most slack
b. The activity with the least slack
c. The activity with the smallest duration
d. The activity with the lowest identification number
e. The activity with the highest cost

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 15:00
The boston hotel high-end linens 600-thread-count sheets coffeemaker and selected teas imported beer fresh-squeezed juices affordability food and drink double-thick bath towels silk pillowcases raw silk curtains with gold embellishments $100/night four-star rooms free snacks, shampoo, and conditioner free wireless internet
Answers: 3
question
Business, 21.06.2019 22:30
Your project team’s recommendations to increase productivity have been approved and your team is now working on an implementation plan. in order to accomplish the plan, several subject matter experts from various parts of the organization have been brought in to assist. you have noticed friction and conflict among team members. some of the disagreement and opposition on your team supports the achievement of team goals and objectives. this type of conflict can be described as:
Answers: 1
question
Business, 22.06.2019 00:50
cranium, inc., purchases term papers from an overseas supplier under a continuous review system. the average demand for a popular mode is 300 units a day with a standard deviation of 30 units a day. it costs $60 to process each order and there is a five−day lead−time. the holding cost for a paper is $0.25 per year and the company policy is to maintain a 98% service level. cranium operates 200 days per year.what is the reorder point r to satisfy a 98% cycleminus−service level? a. greater than 1,700 unitsb. greater than 1,600 units but less than or equal to 1,700 unitsc. greater than 1,500 units but less than or equal to 1,600 unitsd. less than or equal to 1,500 units
Answers: 1
question
Business, 22.06.2019 13:00
Apopular low-cost airline, parson corp., has gone out of business. although the service and price provided by the airline was what customers wanted, the larger airlines were able to drive the low-cost airline out of business through an aggressive price war. which component of the competitive environment does this illustrate? a) threat of new entrants b)competitors c) economic factors d) customers d) regulators
Answers: 1
You know the right answer?
A project leader has realized that two activities in the project cannot be done at the same time bec...
Questions
question
Mathematics, 26.11.2021 23:30
Questions on the website: 13722367