The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.90; actual, $2.03
Standard yards per unit: standard, 4.64 yards; actual, 5.15 yards
Units of production: 9,000
Calculate the direct materials quantity variance.
a. $8,721.00 unfavorable
b. $8,721.00 favorable
c. $9,317.70 unfavorable
d. $9,317.70 favorable

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 19:30
Consider the following two projects. both have costs of $5,000 in year 1. project 1 provides benefits of $2,000 in each of the first four years only. the second provides benefits of $2,000 for each of years 6 to 10 only. compute the net benefits using a discount rate of 6 percent. repeat using a discount rate of 12 percent. what can you conclude from this exercise?
Answers: 3
question
Business, 22.06.2019 23:20
Suppose you manage an upscale restaurant in new york city. would involve writing employee schedules and a list of things to do for the chef and other kitchen staff
Answers: 3
question
Business, 23.06.2019 00:30
How much of your paycheck do you have immediate access to once you deposit it into your bank account a. all of it b. a portion of it c. none of it
Answers: 1
question
Business, 23.06.2019 07:00
Nthis economy, community members typically use simple tools to plant and harvest crops. food supplies are supplemented by hunting animals and gathering plant materials. members trade with each other to obtain needed goods, as few people hold currency. little economic growth occurs. what type of economy is being described?
Answers: 3
You know the right answer?
The following data relate to direct materials costs for February: Materials cost per yard: standard...
Questions
question
Mathematics, 18.10.2019 11:30
question
History, 18.10.2019 11:30
Questions on the website: 13722361