A dependency requiring a design be completed before manufacturing can start is an example of a(n): A. Discretionary Dependency.
B. External dependency.
C. Mandatory dependency.
D. Scope dependency.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:30
Aconsumer values a house at $525,000 and a producer values the same house at $485,000. if the transaction is completed at $510,000, what level of tax rate will result in unconsummated transaction?
Answers: 2
question
Business, 22.06.2019 12:30
land, a building and equipment are acquired for a lump sum of $ 1,000,000. the market values of the land, building and equipment are $ 300,000, $ 800,000 and $ 300,000, respectively. what is the cost assigned to the equipment? (do not round any intermediary calculations, and round your final answer to the nearest dollar.)
Answers: 1
question
Business, 22.06.2019 15:00
Oerstman, inc. uses a standard costing system and develops its overhead rates from the current annual budget.the budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours.(practical capacity is 500,000 hours)annual budgeted overhead costs total $772,800, of which $556,800 is fixed overhead.a total of 119,300 units, using 478,000 direct labor hours, were produced during the year.actual variable overhead costs for the year were $260,400 and actual fixed overhead costs were $555,450.required: 1. compute the fixed overhead spending variance and indicate if favorable or unfavorable.2. compute the fixed overhead volume variance and indicate if favorable or unfavorable.
Answers: 3
question
Business, 22.06.2019 22:00
The company is experiencing an increase in competition, and at the same time they are building more production facilities in southeast asia. in this scenario, the top management team is most likely to multiple choice increase the cost of their products. restructure to reflect a more bureaucratic, stable organization. pull decision-making responsibility from low-level management, taking it on themselves. give lower-level managers the authority to make decisions to benefit the firm. rid themselves of all buffering product.
Answers: 3
You know the right answer?
A dependency requiring a design be completed before manufacturing can start is an example of a(n):...
Questions
question
English, 07.11.2019 04:31
question
History, 07.11.2019 04:31
question
Mathematics, 07.11.2019 04:31
question
Mathematics, 07.11.2019 04:31
Questions on the website: 13722363