A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected that a total of 8 years will be required to complete the work. The firm will buy $600,000 worth of special equipment for the job. During the preparation of the job cost estimate, the following utilization schedule was computed for the special equipment: Year Utilization (hr/yr)
1 6000
2 4000
3 4000
4 1600
5 800
6 800
7 2200
8 2200

At the end of the job, it is estimated that the equipment can be sold at auction for $60,000.

a. Compute the sum-of-years-digits' depreciation schedule.
b. Compute the unit-of-production depreciation schedule

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 03:00
What is the relationship between marginal external cost, marginal social cost, and marginal private cost? a. marginal social cost equals marginal private cost plus marginal external cost. b. marginal private cost plus marginal social cost equals marginal external cost. c. marginal social cost plus marginal external cost equals marginal private cost. d. marginal external cost equals marginal private cost minus marginal social cost. marginal external cost a. is expressed in dollars, so it is not an opportunity cost b. is an opportunity cost borne by someone other than the producer c. is equal to two times the marginal private cost d. is a convenient economics concept that is not real
Answers: 3
question
Business, 22.06.2019 18:00
Match the different financial task to their corresponding financial life cycle phases
Answers: 3
question
Business, 22.06.2019 19:50
The new york company produces high quality chairs. variable manufacturing overhead is applied at a standard rate of $12 per machine hour. each chair requires a standard quantity of six machine hours. production for the month totaled 4,000 units. calculate: the standard cost per unit for variable overhead. select one: a. $130,000 b. $192,000 c. $90,000 d. $100,000
Answers: 2
question
Business, 22.06.2019 21:10
Match the terms with their correct definition. terms: 1. accounts receivable 2. other receivables 3 debtor 4. notes receivable 5. maturity date 6. creditor definitions: a. the party to a credit transaction who takes on an obligation/payable. b. the party who receives a receivable and will collect cash in the future. c. a written promise to pay a specified amount of money at a particular future date. d. the date when the note receivable is due. e. a miscellaneous category that includes any other type of receivable where there is a right to receive cash in the future. f. the right to receive cash in the future from customers for goods sold or for services performed.
Answers: 1
You know the right answer?
A heavy construction firm has been awarded a contract to build a large concrete dam. It is expected...
Questions
question
Mathematics, 23.02.2021 02:10
question
History, 23.02.2021 02:10
question
Mathematics, 23.02.2021 02:10
Questions on the website: 13722363