Given the following production plan, use a chase production strategy to compute the monthly production, ending inventory/(backlog), net requirements and required workforce levels. A worker can produce 75 units per month. Assume that the beginning inventory in January is 750 units, and the firm desires to have 750 units of inventory at the end of June. Month Jan Feb Mar Apr May Jun
Demand 2100 3000 5100 6000 4800 2400

Required:
a. What are the net requirements for January?
b. What month has the highest number of workers required?
c. What is the production level for June?
d. How many people will be employed for the month of January?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
Jurvin enterprises is a manufacturing company that had no beginning inventories. a subset of the transactions that it recorded during a recent month is shown below. $76,700 in raw materials were purchased for cash. $71,400 in raw materials were used in production. of this amount, $66,300 was for direct materials and the remainder was for indirect materials. total labor wages of $151,700 were incurred and paid. of this amount, $134,300 was for direct labor and the remainder was for indirect labor. additional manufacturing overhead costs of $126,300 were incurred and paid. manufacturing overhead of $126,800 was applied to production using the company's predetermined overhead rate. all of the jobs in process at the end of the month were completed. all of the completed jobs were shipped to customers. any underapplied or overapplied overhead for the period was closed to cost of goods sold.required: 1. post the above transactions to t-accounts.2. determine the cost of goods sold for the period.
Answers: 1
question
Business, 22.06.2019 03:40
Apharmaceutical packaging company (ppc) has decided to reorganize its processes into cells. the company has four different production operations, each requiring a unique piece of equipment. the names and functions of the four pieces of equipment are sort, count, place, and package. the company packages five different families of products (a, b, c, d, and e). the tables below indicate the demand (total units/day by product family), required operations, and operation cycle times for each product family. assume that any individual piece of equipment is available to operate 16 hours/day, but 2 hours (in total) are lost each day on each piece of equipment due to breaks and meetings when operators are not available to operate the equipment. how many minutes/day are available for production
Answers: 3
question
Business, 22.06.2019 05:00
The new york stock exchange is an example of what type of stock market?
Answers: 1
question
Business, 22.06.2019 18:50
)a business incurs the following costs per unit: labor $125/unit, materials $45/unit, and rent $250,000/month. if the firm produces 1,000,000 units a month, calculate the following: a. total variable costs b. total fixed costs c. total costs
Answers: 1
You know the right answer?
Given the following production plan, use a chase production strategy to compute the monthly producti...
Questions
question
Mathematics, 06.04.2021 21:00
question
History, 06.04.2021 21:00
Questions on the website: 13722359