JIT/ Continuous Flow / Takt time / Heijunka: A C&A plant makes only two flavors of ice cream– chocolate and vanilla. Each gallon is produced and shipped in discrete containers. The demand for the ice cream (in gallons) is given as follow: Week
Day Chocolate Vanilla
1 20 40
2 60 100
3 30 30
4 50 70
5 10 100

C&A operates 8 hours a day and 5 days a week. Calculate the takt time for this production system; explain how would C&A schedule the production of its ice cream to level demand over the week (i. e., how many gallons of each ice cream flavor would you make in a repeating cycle)?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:30
Which of the following government agencies is responsible for managing the money supply in the united states? a. the u.s. mint b. the federal reserve bank c. congress d. the department of the treasury 2b2t
Answers: 3
question
Business, 22.06.2019 05:30
Identify the three components of a family's culture and provide one example from your own experience
Answers: 2
question
Business, 22.06.2019 07:30
Why has the free enterprise system been modified to include some government intervention?
Answers: 1
question
Business, 22.06.2019 10:40
You were able to purchase two tickets to an upcoming concert for $100 apiece when the concert was first announced three months ago. recently, you saw that stubhub was listing similar seats for $225 apiece. what does it cost you to attend the concert?
Answers: 1
You know the right answer?
JIT/ Continuous Flow / Takt time / Heijunka: A C&A plant makes only two flavors of ice cream– ch...
Questions
question
English, 04.08.2019 10:00
question
Chemistry, 04.08.2019 10:00
Questions on the website: 13722362