Lead time for computers is 5 days with daily demand of 25 and safety stock of 15 computers. If management wants to use 10 kanbans how many computers should each one hold? A) 25.
B) 1.
C) 5.
D) 10.
E) 13.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:30
Achecklists should be based on past
Answers: 1
question
Business, 22.06.2019 06:00
Why might a business based on a fad be a good idea? question 2 options: fads bring in the most customers. some fads are longer lasting than expected. fads have made some business owners incredibly wealthy. fads can take a business in a new direction.
Answers: 2
question
Business, 22.06.2019 09:00
Harry is 25 years old with a 1.55 rating factor for his auto insurance. if his annual base premium is $1,012, what is his total premium? $1,568.60 $2,530 $1,582.55 $1,842.25
Answers: 3
question
Business, 23.06.2019 00:20
E11-2 (multiple choice) identify the best answer for each of the following: which of the following statements about internal service fund liabilities is false? internal service funds may report both current and long-term liabilities. internal service funds may not issue bonds for financing purposes. internal service funds may report contingent liabilities. due to other funds would be reported as a current liability
Answers: 3
You know the right answer?
Lead time for computers is 5 days with daily demand of 25 and safety stock of 15 computers. If manag...
Questions
question
Mathematics, 06.07.2021 19:00
question
English, 06.07.2021 19:00
question
History, 06.07.2021 19:00
question
Mathematics, 06.07.2021 19:00
Questions on the website: 13722363