1. (a) Fill out the following MRP record for Part C. Part C
Week
1 2 3 4 5 6
Gross requirements 35 40 40 40 40 45
Scheduled receipts 30
Projected available balance 40 35 25 15 5 25 10
Planned receipts 0 30 30 30 60 30
Planned order releases 30 30 30 60 30 0
Lot size=30, LT=1, SS=0
1 (b) Given the above MRP record and the following routing data for Part C, determine the capacity requirements for work center 100 from Part A using CRP. For the scheduled receipt of 30 units in week 1, assume that the setup and half of the quantity have been completed.
Routing Data for Part C
Operation Work Center Setup Time Run Time
Operation 1 100 2 hours 0.2 hour
Capacity requirements for work center 100 from Part C
Week
1 2 3 4 5 6
Hours of Capacity
2. The following input/output data were gathered at the end of week 4 for a work center.
Week
1 2 3 4
Planned Input 60 60 60 60
Actual Input 68 70 75 70
Cumulative Deviation 8 18 33 43
Planned Output 65 65 65 65
Actual Output 60 62 63 65
Cumulative Deviation -5 -8 -10 -12
Planned Backlog 30
Actual Backlog 30
(a) Complete the input/output document.
(b) What recommendations would you make?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 16:30
The movement of an economy from one condition to another and back again
Answers: 2
question
Business, 22.06.2019 12:30
Acorporation a. can use different depreciation methods for tax and financial reporting purposes b. must use the straight - line depreciation method for tax purposes and double declining depreciation method financial reporting purposes c. must use different depreciation method for tax purposes, but strictly mandated depreciation methods for financial reporting purposes d. can use straight- line depreciation method for tax purposes and macrs depreciation method financial reporting purposes
Answers: 2
question
Business, 22.06.2019 17:00
Explain how can you avoid conflict by adjusting
Answers: 1
question
Business, 22.06.2019 19:20
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to power a small isolated plant. assume we want to add a precompressor, which (when isolated and estimated separately) currently costs $13291. determine the total cost of the 120-kw unit. (hint: skip $ and comma symbols)
Answers: 3
You know the right answer?
1. (a) Fill out the following MRP record for Part C. Part C
Week
1 2 3 4 5 6
Gros...
Questions
Questions on the website: 13722360