The bill of material (BOM) for Fitter Snacker’s NRG bars (One batch of 500 lbs) IngredientNRG-ANRG-B
Oats (lb.)300250
Wheat germ (lb.)5050
Cinnamon (lb.)55
Nutmeg (lb.)22
Cloves (lb.)11
Honey (gal.)1010
Canola Oil (gal.)77
Vit./min. powder (lb.)55
Carob chips (lb.)50
Raisins (lb.)50
Protein Powder (lb.) 50
Hazelnuts (lb.) 30
Dates (lb.) 70
Projected sales of each nutrient bar is give in the table as follow (1 case of nutrient bar equivalent to 72 lbs)
Wheat Germ LT = 1 week
Week 1
Week 2
Week 3
Week 4
Week 5
MPS
NRG-A
752
940
940
940
984
(cases)
NRG-B
322
403
403
403
422
Solve the requirement of canola oil with the information given above. there is one scheduled receipt on week 1 of 2,000 gal and there is an inventory on-hand of 1,200 to start with. All orders must be in multiples of 2,000 gal, give your planned orders in order to fulfill the projected production schedule (lead time for Canola Oil is 3 week).
Do the same for requirement of honey, given that there is a scheduled receipt on week 1 of 2000 gal, inventory on hand is 2000 gal, and the lead time for honey is two week. All orders have to be in multiples of 1000 gal (honey container size).
~Please include screenshots of your excel document and formulas.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 00:30
Needs to schedule the staffing of the center. it is open from 8am until midnight. larry has monitored the usage of the center at various times of the day and determined that the following number of computer consultants are required: time of dayminimum number of consultants required to be on duty8 am-noon4noon-4 pm84pm-8pm108pm-midnight6 two types of computer consultants can be hired: full-time and part-time. the full- time consultants work for eight consecutive hours in any of the shifts: morning (8am- 4pm), afternoon (noon-8pm) and evening (4pm-midnight). full-time consultants are paid $14 per hour. part-time consultants can be hired to work any of the four shifts listed in the table. part-time consultants are paid $12 per hour. an additional requirement is that during every time period, there must be at least two full-time consultants on duty for every part-time consultant on duty. larry would like to determine how many full-time and part-time consultants should work each shift to meet the above requirements at the minimum possible cost. formulate this as an lp problem. you must define your variables clearly
Answers: 2
question
Business, 22.06.2019 13:30
You operate a small advertising agency. you employ two secretaries, a graphic designer, three sales representatives, and an office coordinator. 1. what types of things would you consider when determining how to compensate each position? describe two (2) considerations. 2. what type of compensation plan would you use for each position?
Answers: 1
question
Business, 22.06.2019 13:30
Over the past year, three of the star salesmen at family resorts international's corporate office have been lured away to competitors. on top of that, karina, the general manager of the sales department, has noticed that most employees come in, do their jobs, and leave. family resorts offers a good salary, benefits, and tuition reimbursement, as well as a number of development and training programs. most employees seem contented enough, but karina would like to do something to increase the level of engagement among her staff. what do you think karina should do?
Answers: 1
question
Business, 22.06.2019 21:50
Labor unions have used which of the following to win passage of favorable laws such as shorter work weeks and the minimum wage? a. strikes b. collective bargaining c. lobbying d. lockouts
Answers: 1
You know the right answer?
The bill of material (BOM) for Fitter Snacker’s NRG bars (One batch of 500 lbs) IngredientNRG-ANRG-...
Questions
question
History, 06.10.2019 18:00
Questions on the website: 13722361