On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of $3,800,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required:
a. Calculate the amount Of revenue and gross profit or loss to be recognized in each of the three years.
b. Prepare journal entries for 2021 to record the transactions described (credit "various accounts' for construction costs incurred).
c. Prepare journal entries for 2022 to record the transactions described (credit •various accounts" for construction costs incurred).
d. Prepare a partial balance sheet to show the presentation Of the project as Of December 31, 2021.
e. Prepare a partial balance sheet to show the presentation of the project as of December 31. 2022.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 17:30
Emery pharmaceutical uses an unstable chemical compound that must be kept in an environment where both temperature and humidity can be controlled. emery uses 825 pounds per month of the chemical, estimates the holding cost to be 50% of the purchase price (because of spoilage), and estimates order costs to be $48 per order. the cost schedules of two suppliers are as follows: vendor 1 vendor 2 quantity price/lb quantity price/lb 1-499 $17 1-399 $17.10 500-999 $16.75 400-799 $16.85 1000+ $16.50 800-1199 $16.60 1200+ $16.25 (a) what is the economic order quantity for each supplier? (b) what quantity should be ordered and which supplier should be used? (c) the total cost for the most economic order sire is $
Answers: 2
question
Business, 22.06.2019 20:30
What talent or skill do u wish too develop for yourself
Answers: 1
question
Business, 22.06.2019 22:30
Ellen and george work for the same company. ellen, a gen xer, really appreciates the flextime opportunities, while george, a baby boomer, takes advantage of the free computer training offered at the company. these policies are examples of
Answers: 3
question
Business, 22.06.2019 23:30
Shelby bought her dream car, a 1966 red convertible mustang, with a loan from her credit union. if shelby paid 5.1% and the bank earned a real rate of return of 3.5%, what was the inflation rate over the life of the loan?
Answers: 2
You know the right answer?
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to b...
Questions
question
Spanish, 10.04.2020 05:17
question
Chemistry, 10.04.2020 05:17
question
English, 10.04.2020 05:17
Questions on the website: 13722363