subject
Business, 01.05.2021 16:00 MacieKay8865

A copy machine is available 18 hours a day. On a typical day, the machine needs to process 320 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 25% of the jobs need to be reworked, in which the set?up time and the processing time have to be repeated once. In the remaining time, the equipment is idle. You would need to show steps and use 2 decimals in calculations. (a) Draw a tree diagram to show the breakdown of equipment time.
(b) Define and calculate total non value added time in minutes.
(c) Define and calculate total value added time in minutes.
(d) Calculate total waste time in minutes. Give a detailed breakdown of waste time.
(e) What is the OEE of the equipment? (percentage, 2 decimals, i. e. 23.67%)

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 08:40
Calculate the cost of each capital component—in other words, the after-tax cost of debt, the cost of preferred stock (including flotation costs), and the cost of equity (ignoring flotation costs). use both the capm method and the dividend growth approach to find the cost of equity.calculate the cost of new stock using the dividend growth approach.what is the cost of new common stock based on the capm? (hint: find the difference between re and rs as determined by the dividend growth approach and then add that difference to the capm value for rs.)assuming that gao will not issue new equity and will continue to use the same target capital structure, what is the company’s wacc? e. suppose gao is evaluating three projects with the following characteristics.each project has a cost of $1 million. they will all be financed using the target mix of long-term debt, preferred stock, and common equity. the cost of the common equity for each project should be based on the beta estimated for the project. all equity will come from reinvested earnings.equity invested in project a would have a beta of 0.5 and an expected return of 9.0%.equity invested in project b would have a beta of 1.0 and an expected return of 10.0%.equity invested in project c would have a beta of 2.0 and an expected return of 11.0%.analyze the company’s situation, and explain why each project should be accepted or rejected g
Answers: 1
question
Business, 22.06.2019 09:40
Boone brothers remodels homes and replaces windows. ace builders constructs new homes. if boone brothers considers expanding into new home construction, it should evaluate the expansion project using which one of the following as the required return for the project?
Answers: 1
question
Business, 22.06.2019 16:10
The brs corporation makes collections on sales according to the following schedule: 30% in month of sale 66% in month following sale 4% in second month following sale the following sales have been budgeted: sales april $ 130,000 may $ 150,000 june $ 140,000 budgeted cash collections in june would be:
Answers: 1
question
Business, 22.06.2019 17:30
According to management education expert ashok rao, companies can increase their profitability by through careful inventory management. a. 5% to 10% b. 10% to 25% c. 20% to 50% d. 75%
Answers: 1
You know the right answer?
A copy machine is available 18 hours a day. On a typical day, the machine needs to process 320 jobs....
Questions
question
Computers and Technology, 03.09.2021 18:00
question
Mathematics, 03.09.2021 18:00
question
Social Studies, 03.09.2021 18:00
Questions on the website: 13722367