Appendix: Normal and Abnormal Spoilage in Process Costing Novel Toys, Inc., manufactures plastic water guns. Each gun's left and right frames are produced in the Molding Department. The left and right frames are then transferred to the Assembly Department where the trigger mechanism is inserted and the halves are glued together. (The left and right halves together define the unit of output for the Molding Department.) In June, the Molding Department reported the following data:
In the Molding Department, all direct materials are added at the beginning of the process.
Beginning work in process consisted of 3,000 units, 20 percent complete with respect to direct labor and overhead. Costs in beginning inventory included direct materials, $450; and conversion costs, $138.
Costs added to production during the month were direct materials, $950; and conversion costs, $2,174.50.
Inspection takes place at the end of the process. Malformed units are discarded. All spoilage is considered abnormal.
During the month, 7,000 units were started, and 8,000 good units were transferred out to Finishing. All other units finished were malformed and discarded. There were 1,000 units that remained in ending work in process, 25 percent complete.
Required:
1. Prepare a physical flow schedule.
Novel Toys, Inc.
Physical Flow Schedule
Units to account for:
Units, beginning work in process
Units started
Total units to account for
Units accounted for:
Units transferred out
Units spoiled
Units, ending work in process
Total units accounted for
Feedback
1. The physical flow schedule traces the units in process regardless of their stage of completion.
2. Calculate equivalent units of production using the weighted average method.
Equivalent Units
Direct Materials
Conversion Costs
3. Calculate the unit cost. Round your answer to the nearest cent.
$ per unit
4. What is the cost of goods transferred out?
$
What is the ending work in process? Round your answer to the nearest cent.
$
What is the loss due to spoilage?
$
Feedback
2. To calculate equivalent units, weighted average counts prior-period output in BWIP as belonging to the current period. All units are output in the current period.
3. The unit cost is obtained by dividing the sum of the costs in BWIP and the current-period costs by the weighted average equivalent output.
4. Costing out ending work in process is done by computing the cost of each input and then adding to obtain the total. The valuation of cost of goods transferred out is simplified as it is the total unit cost multiplied by the units completed.
5. Prepare the journal entry to remove spoilage from the Molding Department.
Loss from Abnormal Spoilage
Work in Process-Molding

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 08:00
Why do police officers get paid less than professional baseball players?
Answers: 2
question
Business, 22.06.2019 20:30
Caleb construction (cc) incurs supervisor salaries expense in the construction of homes. if cc manufactures 100 homes in a year, fixed supervisor salaries will be $400,000. with the current construction supervisors, cc's productive capacity is 150 homes in a year. however, if cc is contracts to build more than 150 homes per year, it will need to hire additional supervisors, which are hired as full-time rather than temporary employees. cc's productive capacity would then become 200 homes per year, and salaries expense would increase to $470,000. how would cc’s salaries expense be properly classified? fixed variable mixed stepped curvilinear
Answers: 3
question
Business, 22.06.2019 21:30
Sunset foods relies on a highly centralized functional structure to ensure consistency in the quality and taste of its products and to drive down costs via process innovations. however, as a consequence of its highly compartmentalized structure, the firm has found it difficult to transfer information and ideas from one department to the next. with the launch of its new line of breakfast foods coming up, how can sunset improve its ability to collaborate without sacrificing the benefits of its current structure
Answers: 1
question
Business, 22.06.2019 21:40
Heather has been an active participant in a defined benefit plan for 19 years. during her last 6 years of employment, heather earned $42,000, $48,000, $56,000, $80,000, $89,000, and $108,000, respectively (representing her highest-income years). calculate heather’s maximum allowable benefits from her qualified plan (assume that there are fewer than 100 participants). assume that heather’s average compensation for her three highest years is $199,700. calculate her maximum allowable benefits.
Answers: 3
You know the right answer?
Appendix: Normal and Abnormal Spoilage in Process Costing Novel Toys, Inc., manufactures plastic wa...
Questions
Questions on the website: 13722362