subject
Business, 05.04.2021 23:50 Smays6903

A contractor is planning to pour concrete on Monday morning, but he has heard a weather forecast that rain is expected. The probabilities of rain are 0.8 on Monday, 0.6 on Tuesday, 0.3 on Wednesday, and 0.1 on Thursday and each succeeding day for five days. If it rains on the day that concrete is poured, there will be an immediate 50,000 damage cost and a delay of five days in the construction schedule. For every day of delay, 20,000 is lost. The delay cost applies even if it is the contractor who decides to delay the pour. Required:
a. Determine on which day the concrete should be poured.
b. What is the associated expected cost?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:00
Sheldon has the following year-end account balances: accounts receivable, $5,000; supplies, $12,000; equipment, $18,000; accounts payable, $17,000; stockholders’ equity, $43,000. the cash account balance was not available at year-end. given the account balances listed, the balance in the cash account should be?
Answers: 2
question
Business, 22.06.2019 05:00
Which of the following differentiates cost accounting and financial accounting? a. the primary users of cost accounting are the investors, whereas the primary users of financial accounting are the managers. b. cost accounting measures only the financial information related to the costs of acquiring fixed assets in an organization, whereas financial accounting measures financial and nonfinancial information of a company's business transactions. c. cost accounting measures information related to the costs of acquiring or using resources in an organization, whereas financial accounting measures a financial position of a company to investors, banks, and external parties. d. cost accounting deals with product design, production, and marketing strategies, whereas financial accounting deals mainly with pricing of the products.
Answers: 3
question
Business, 22.06.2019 10:00
Your father offers you a choice of $120,000 in 11 years or $48,500 today. use appendix b as an approximate answer, but calculate your final answer using the formula and financial calculator methods. a-1. if money is discounted at 11 percent, what is the present value of the $120,000?
Answers: 3
question
Business, 22.06.2019 11:00
Consider an economy where government expenditures are 10 and total tax revenues are 10. the supply of labor is fixed at 125 and the supply of capital is fixed at 8. the economy is described by the following equations. y k to the power of 1 divided by 3 end exponent l to the power of 2 divided by 3 end exponent c 2.5 + 0.75 ( y - t ) i 10 - 0.5 r the level of private savings is
Answers: 1
You know the right answer?
A contractor is planning to pour concrete on Monday morning, but he has heard a weather forecast tha...