Business, 18.03.2021 01:20 Johnson926

Early in 2021, the Excalibur Company began developing a new software package to be marketed. The project was completed in December 2021 at a cost of $54 million. Of this amount, $36 million was spent before technological feasibility was established. Excalibur expects a useful life of five years for the new product with total revenues of $90 million. During 2022, revenue of $27 million was recognized. Required:
1. Prepare a journal entry to record the 2021 development costs.
2. Calculate the required amortization for 2022.
3. Determine the amount to report for the computer software costs in the December 31, 2022, balance sheet.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:20
“wonderful! not only did our salespeople do a good job in meeting the sales budget this year, but our production people did a good job in controlling costs as well,” said kim clark, president of martell company. “our $11,150 overall manufacturing cost variance is only 3% of the $1,536,000 standard cost of products made during the year. that’s well within the 3% parameter set by management for acceptable variances. it looks like everyone will be in line for a bonus this year.” the company produces and sells a single product. the standard cost card for the product follows: standard cost card—per unit direct materials, 4.00 feet at $4.00 per foot $ 16.00 direct labor, 1.1 direct labor-hours at $13 per direct labor-hour 14.30 variable overhead, 1.1 direct labor-hours at $2.40 per direct labor-hour 2.64 fixed overhead, 1.1 direct labor-hours at $6.50 per direct labor-hour 7.15 standard cost per unit $ 40.09the following additional information is available for the year just completed: a. the company manufactured 20,000 units of product during the year.b. a total of 77,000 feet of material was purchased during the year at a cost of $4.25 per foot. all of this material was used to manufacture the 20,000 units. there were no beginning or ending inventories for the year.c. the company worked 24,000 direct labor-hours during the year at a direct labor cost of $12.50 per hour.d. overhead is applied to products on the basis of standard direct labor-hours. data relating to manufacturing overhead costs follow: denominator activity level (direct labor-hours) 19,000 budgeted fixed overhead costs $ 123,500 actual variable overhead costs incurred $ 64,800 actual fixed overhead costs incurred $ 120,900required: 1. compute the materials price and quantity variances for the year. (round standard price and actual price to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i.e., zero 2. compute the labor rate and efficiency variances for the year. (round standard rate and actual rate to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i.e., zero 3. for manufacturing overhead compute: a. the variable overhead rate and efficiency variances for the year. (round standard rate and actual rate to 2 decimal places. indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i.e., zero b. the fixed overhead budget and volume variances for the year. (indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i.e., zero
Answers: 2
question
Business, 22.06.2019 07:10
In a team environment, a coordinator is? a person with expert knowledge or skills in a particular area the team needs. a good listener who works to resolve social problems among teammates. a leader who team members focus on their tasks. a good networker who likes to explore new ideas and possiblities.
Answers: 2
question
Business, 22.06.2019 08:40
Which of the following is not a characteristic of enterprise applications that cause challenges in implementation? a. they introduce "switching costs," making the firm dependent on the vendor. b. they cause integration difficulties as every vendor uses different data and processes. c. they are complex and time consuming to implement. d. they support "best practices" for each business process and function. e. they require sweeping changes to business processes to work with the software.
Answers: 1
question
Business, 22.06.2019 10:30
What type of budget is stated? a budget is a type of financial report that scrutinizes the inflow and outflow of money in a given financial year.
Answers: 1
You know the right answer?
Early in 2021, the Excalibur Company began developing a new software package to be marketed. The pro...
Questions
Questions on the website: 13722361