Nair Corp. enters into a contract with a customer to build an apartment building for $1,000,000. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $150,000 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $50,000 each week that completion is delayed. Nair commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability
August 1, 2021 70 %
August 8, 2021 20
August 15, 2021 5
After August 15, 2021 5
(a) Determine the transaction price for the contract, assuming Nair is only able to estimate whether the building can be completed by August 1, 2021, or not (Nair estimates that there is a 70% chance that the building will be completed by August 1, 2021). (If answer is 0, please enter 0. Do not leave any fields blank.)
(b) Determine the transaction price for the contract, assuming Nair has limited information with which to develop a reliable estimate of completion by the August 1, 2021, deadline.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 16:30
Who got instagram! ? if you do give it to me
Answers: 1
question
Business, 22.06.2019 19:30
Consider the following two projects. both have costs of $5,000 in year 1. project 1 provides benefits of $2,000 in each of the first four years only. the second provides benefits of $2,000 for each of years 6 to 10 only. compute the net benefits using a discount rate of 6 percent. repeat using a discount rate of 12 percent. what can you conclude from this exercise?
Answers: 3
question
Business, 22.06.2019 19:30
Adisadvantage of corporations is that shareholders have to pay on profits.
Answers: 1
question
Business, 22.06.2019 20:00
Miller mfg. is analyzing a proposed project. the company expects to sell 14,300 units, plus or minus 3 percent. the expected variable cost per unit is $15 and the expected fixed cost is $35,000. the fixed and variable cost estimates are considered accurate within a plus or minus 3 percent range. the depreciation expense is $32,000. the tax rate is 34 percent. the sale price is estimated at $19 a unit, give or take 3 percent. what is the net income under the worst case scenario?
Answers: 2
You know the right answer?
Nair Corp. enters into a contract with a customer to build an apartment building for $1,000,000. The...
Questions
question
Health, 25.10.2019 13:43
question
Advanced Placement (AP), 25.10.2019 13:43
Questions on the website: 13722367