The operator of a rock quarry is invited to bid on furnishing 3,500 CY of aggregate for a job. The gravel is to be delivered to a job, which is 12 mi from the quarry. The aggregate will be loaded into trucks by a loader that can load at a rate of 80 cy/hr. The trucks will haul 12 cy/load and average 35 mi/hour loaded and 45 mi/hour empty. The estimated time to dump a load is 5 min. Assume 45 min/hr efficiency for the loading and hauling operation. The cost information for the job is:
Royalty paid for aggregate = $1.35/cy
Overhead = $0.75/cy
Profit = $1.20/cy
Loader = $85.00/hr
Operator = $32.00/hr
Trucks, each = $55.00/hr
Truck driver, each = $28.00/hr
Foremen = $35.00/hr

Required:
What should be the bid price per cubic yard?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 18:40
Reactive power generation has the following capital structure. its corporate tax rate is 40%. security market value required rate of return debt $ 30 million 4 % preferred stock 30 million 6 common stock 40 million 10 what is its wacc? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.)
Answers: 2
question
Business, 21.06.2019 19:30
Consumer surplus is: the difference between the price of a product and what consumers were willing to pay for the product. the difference between the discounted price of a product and its retail price. the difference between the price paid by consumers and the price required of producers. the difference between the price of a product and consumers' valuation of the last unit of the product purchased.
Answers: 2
question
Business, 22.06.2019 02:40
Which critical success factor improves with reduced cycle time, better quality standards, and improved efficiency when an is is implemented?
Answers: 3
question
Business, 22.06.2019 22:40
Utilization will always be lower than efficiency because: a. effective capacity is greater than design capacityb. expected output is less than actual output.c. effective capacity equals design capacity.d. effective capacity is less than design capacity.e. expected output is less than rated capacity.
Answers: 3
You know the right answer?
The operator of a rock quarry is invited to bid on furnishing 3,500 CY of aggregate for a job. The g...
Questions
Questions on the website: 13722363