Quick Step Company is debating the use of direct labor cost or direct labor hours as the cost allocation base for allocating manufacturing overhead. The following information is available for the most recent year: Estimated direct labor cost $500,300
Actual direct labor cost $465,700
Estimated manufacturing overhead costs $425,800
Actual manufacturing overhead costs $350,000
Estimated direct labor hours 250,200
Actual direct labor hours 232,800
If Quick Step Company uses direct labor hours as the allocation base, what would the predetermined manufacturing overhead rate be?
A. $720,366$720,366.B. $399,900$399,900.C. $436,880$436,880.D. $350,100$350,100.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 14:40
Increases in output and increases in the inflation rate have been linked to
Answers: 2
question
Business, 22.06.2019 17:00
Cadbury has a chocolate factory in dunedin, new zealand. for easter, it makes two kinds of “easter eggs”: milk chocolate and dark chocolate. it cycles between producing milk and dark chocolate eggs. the table below provides data on these two products. demand (lbs per hour) milk: 500 dark: 200 switchover time (minutes) milk: 60 dark: 30 production rate per hour milk: 800 dark: 800 for example, it takes 30 minutes to switch production from milk to dark chocolate. demand for milk chocolate is higher (500lbs per hour versus 200 lbs per hour), but the line produces them at the same rate (when operating): 800 lbs per hour. a : suppose cadbury produces 2,334lbs milk chocolate and 1,652 lbs of dark chocolate in each cycle. what would be the maximum inventory (lbs) of milk chocolate? b : how many lbs of milk and dark chocolate should be produced with each cycle so as to satisfy demand while minimizing inventory?
Answers: 2
question
Business, 22.06.2019 20:20
Precision aviation had a profit margin of 6.25%, a total assets turnover of 1.5, and an equity multiplier of 1.8. what was the firm's roe? a. 15.23%b. 16.03%c. 16.88%d. 17.72%e. 18.60%
Answers: 2
question
Business, 22.06.2019 20:40
Review the wbs and gantt chart you created previously. propose three to five additional activities that would you estimate resources and durations. now, identify at least eight milestones for the recreation and wellness intranet project. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone. add your activities and milestones to your gantt chart, creating a new gantt chart. estimate the task durations and enter dependencies as appropriate. remember that your schedule goal for the project is six months. copy the gantt chart and network diagram to a word document.
Answers: 2
You know the right answer?
Quick Step Company is debating the use of direct labor cost or direct labor hours as the cost alloca...
Questions
question
World Languages, 25.11.2021 14:00
question
History, 25.11.2021 14:00
question
Advanced Placement (AP), 25.11.2021 14:00
Questions on the website: 13722362