We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 10:00
Suppose an economy has only two sectors: goods and services. each year, goods sells 80% of its outputs to services and keeps the rest, while services sells 62% of its output to goods and retains the rest. find equilibrium prices for the annual outputs of the goods and services sectors that make each sector's income match its expenditures.
Answers: 2
question
Business, 22.06.2019 17:30
Alinguist had a gross income of 53,350 last year. if 17.9% of his income got witheld for federal income tax, how much of the linguist's pay got witheld for federal income tax last year?
Answers: 2
question
Business, 22.06.2019 19:00
Question 55 ted, a supervisor for jack's pool supplies, was accused of stealing pool supplies and selling them to friends and relatives at reduced prices. given ted's earlier track record, he was not fired immediately. the authorities decided to give him an administrative leave, without pay, until the investigation was complete. in view of the given information, it would be most appropriate to say that ted was: demoted. discharged. suspended. dismissed.
Answers: 2
question
Business, 22.06.2019 19:00
The demand curve determines equilibrium price in a market. is a graphical representation of the relationship between price and quantity demanded. depicts the relationship between production costs and output. is a graphical representation of the relationship between price and quantity supplied.
Answers: 1
You know the right answer?
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no prece...
Questions
question
Business, 24.03.2021 04:10
question
Mathematics, 24.03.2021 04:10
question
Business, 24.03.2021 04:10
question
Mathematics, 24.03.2021 04:10
question
Spanish, 24.03.2021 04:10
question
Health, 24.03.2021 04:10
Questions on the website: 13722360