Consider the following process that makes customized suits. When an order is placed, measurement is taken, which takes 30 minutes to complete. After taking the measurement, materials are prepared and cut, and this takes one hour. Once the materials are prepared and cut, the materials are sewed. Sewing takes 2.5 hours on average per order. The process operates for 10 hours a day. The following picture summarizes the process. 1. What is the capacity of the process in [suits/day]?
2. Assume that the demand for the customized suit is 0.2[suits/hour]. What should the flow rate of the process be in [suits/day]?
3. Assume that the demand for the customized suit is 0.5[suits/hour]. What is the implied utilization (in %) of the Sewing stage?
4. Assume that the demand for the customized suit is 0.5[suits/hour]. What is the utilization (in %) of the Measuring stage?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 03:30
Acrosswalk_when there are no pavement markings.
Answers: 1
question
Business, 22.06.2019 11:30
Leon and sara are arguing over when the best time is to degrease soup. leon says that it's easiest to degrease soup when it's boiling. sara says it's easiest to degrease soup when it's cold. who is correct? a. neither leon nor sara is correct. b. leon is correct. c. both leon and sara are correct. d. sara is correct. student b   incorrect which following answer correct?
Answers: 1
question
Business, 22.06.2019 17:30
Which curve shows increasing opportunity cost as you give up more of one option? demand curve bow-shaped curve yield curve indifference curve
Answers: 3
question
Business, 22.06.2019 20:20
Direct materials (4.2 x $15) $ 63direct labor ($12 x 17.5) $210manufacturing overhead ($2.40 x 17.5) $42total job cost $ 315dougan, inc. allocates overhead based on a predetermined overhead rate of $2.40 per direct labor hour. employees are paid $12.00 per hour. job 24 requires 4.2 pounds of direct materials at a cost of $15.00 per pound. employees worked a total of 17.5 hours to complete the job. actual manufacturing overhead costs totaled $80,000 for the year for the company. how much is the cost of job 24?
Answers: 1
You know the right answer?
Consider the following process that makes customized suits. When an order is placed, measurement is...
Questions
question
Mathematics, 28.05.2021 19:40
question
Mathematics, 28.05.2021 19:40
question
Health, 28.05.2021 19:40
question
Chemistry, 28.05.2021 19:40
Questions on the website: 13722367