On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3
Costs incurred $720,000 $1,170,000 $1,110,000
Expected future costs $1,680,000 $810,000 $0

For this long-term construction contract, the contractor needs to calculate the estimated dollar values of the revenue and gross profit (loss) to be recognized each year. Complete the contractor's long-term construction contract using the information above. Write the appropriate amounts in the associated cells. Indicate losses by using a leading minus (-) sign. Round all amounts to the nearest dollar. If no entry is necessary, enter a zero (0).

Revenue Gross profit (loss)
Year 1
Year 2

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 01:30
For each example identify the most appropriate ctso
Answers: 3
question
Business, 22.06.2019 11:00
When partners own different portions of the business, the terms should be stated clearly in what document? the articles of incorporation the executive summary the business summary the partnership agreement
Answers: 3
question
Business, 22.06.2019 23:00
Draw a flowchart for a process of interest to you, such as a quick oil-change service, a factory process you might have worked in, ordering a pizza, renting a car or truck, buying products on the internet, or applying for an automobile loan. identify the points where something (people, information) waits for service or is held in work-in-process inventory, the estimated time to accomplish each activity in the process, and the total flow time. evaluate how well the process worked and what might be done to improve it.
Answers: 2
question
Business, 23.06.2019 06:10
Which steps would you take to determine how much an employee should be paid? select all that apply. determine the number of hours the employee was scheduled to work. determine the number of hours the employee worked. determine whether the employee worked overtime hours. determine whether any of the days worked are holidays that receive holiday overtime payment rates. determine the hourly rate this employee earns. determine whether this is a new employee.
Answers: 1
You know the right answer?
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expect...
Questions
Questions on the website: 13722359