Consider a four-step serial process with processing times given in the list below. There is one machine at each step of the process and this is a machine-paced process. Step 1: 26 minutes per unit
Step 2: 16 minutes per unit
Step 3: 23 minutes per unit
Step 4: 26 minutes per unit

Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 91 units?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 17:00
During which of the following phases of the business cycle does the real gdp fall? a. trough b. expansion c. contraction d. peak
Answers: 2
question
Business, 22.06.2019 21:00
Ryan terlecki organized a new internet company, capuniverse, inc. the company specializes in baseball-type caps with logos printed on them. ryan, who is never without a cap, believes that his target market is college and high school students. you have been hired to record the transactions occurring in the first two weeks of operations.
Answers: 1
question
Business, 22.06.2019 21:40
Which of the following distribution systems offers speed and reliability when emergency supplies are needed overseas? a. railroadsb. airfreightc. truckingd. pipelinese. waterways
Answers: 2
question
Business, 22.06.2019 22:50
For 2016, gourmet kitchen products reported $22 million of sales and $19 million of operating costs (including depreciation). the company has $15 million of total invested capital. its after-tax cost of capital is 10%, and its federal-plus-state income tax rate was 36%. what was the firm’s economic value added (eva), that is, how much value did management add to stockholders’ wealth during 2016?
Answers: 1
You know the right answer?
Consider a four-step serial process with processing times given in the list below. There is one mach...
Questions
question
Chemistry, 17.04.2020 02:14
Questions on the website: 13722360