Business, 29.01.2021 16:00 joshsmith2022

Alton Company uses a process-costing system for its single product. Material A is added at the beginning of the process; in contrast, material B is added when the units are 75% complete. The firm's ending work-in-process inventory consists of 6,000 units that are 80% complete. Which of the following correctly expresses the equivalent units of production with respect to materials A and B in the ending work-in-process inventory? a. A, 4,800; B, 0.
b. A, 4,800; B, 4,800.
c. A, 6,000; B, 0.
d. A, 6,000; B, 4,800.
e. A, 6,000; B, 6,000.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 17:00
Aaron corporation, which has only one product, has provided the following data concerning its most recent month of operations: selling price $ 102 units in beginning inventory 0 units produced 4,900 units sold 4,260 units in ending inventory 640 variable costs per unit: direct materials $ 20 direct labor $ 41 variable manufacturing overhead $ 5 variable selling and administrative expense $ 4 fixed costs: fixed manufacturing overhead $ 64,200 fixed selling and administrative expense $ 2,900 the total contribution margin for the month under variable costing is:
Answers: 2
question
Business, 22.06.2019 21:00
Dozier company produced and sold 1,000 units during its first month of operations. it reported the following costs and expenses for the month: direct materials $ 69,000 direct labor $ 35,000 variable manufacturing overhead $ 15,000 fixed manufacturing overhead 28,000 total manufacturing overhead $ 43,000 variable selling expense $ 12,000 fixed selling expense 18,000 total selling expense $ 30,000 variable administrative expense $ 4,000 fixed administrative expense 25,000 total administrative expense $ 29,000 required: 1. with respect to cost classifications for preparing financial statements: a. what is the total product cost
Answers: 2
question
Business, 22.06.2019 22:40
Utilization will always be lower than efficiency because: a. effective capacity is greater than design capacityb. expected output is less than actual output.c. effective capacity equals design capacity.d. effective capacity is less than design capacity.e. expected output is less than rated capacity.
Answers: 3
question
Business, 22.06.2019 23:00
The sign at the bank reads, "wait here for the first available teller," suggests the use of a waiting line system.a. multiple server, single phaseb. random server, single phasec. single server, multiphased. multiple server, multiphasee. dynamic server, single phase
Answers: 2
You know the right answer?
Alton Company uses a process-costing system for its single product. Material A is added at the begin...
Questions
question
Mathematics, 29.01.2021 18:50
question
Mathematics, 29.01.2021 18:50
question
Mathematics, 29.01.2021 18:50
question
Advanced Placement (AP), 29.01.2021 18:50
Questions on the website: 13722363