1. It is said that a delay in critical path activity will delay the project, while a delay in a noncritical path activity will not necessarily delay the project. Explain the need to specify "not necessarily." 2. Why does a project necessarily have to possess some form of deadline? What is the implication of a project without a deadline?
3. Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of three days, and task B has an early finish time of five days. Task C is two days long. What is the early finish time of task C?
4. Task E has an early start time of three days and an early finish time of five days, while it also has a late start time of ten days and a late finish time of 12 days from now. What is the slack in task E?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 05:20
What are the general categories of capital budget scenarios? describe the overall decision-making context for each.
Answers: 3
question
Business, 22.06.2019 11:10
The green fiddle has declared a $5 per share dividend. suppose capital gains are not taxed, but dividends are taxed at 15 percent. new irs regulations require that taxes be withheld at the time the dividend is paid. green fiddle stock sells for $71.50 per share, and the stock is about to go ex-dividend. what will the ex-dividend price be?
Answers: 2
question
Business, 22.06.2019 16:00
If the family’s net monthly income is 7,800 what percent of the income is spent on food clothing and housing?
Answers: 3
question
Business, 22.06.2019 16:10
The following are line items from the horizontal analysis of an income statement:increase/ (decrease) increase/ (decrease) 2017 2016 amount percent fees earned $120,000 $100,000 $20,000 20% wages expense 50,000 40,000 10,000 25 supplies expense 2,000 1,700 300 15 which of the items is stated incorrectly? a. fees earned b. supplies expense c. none of these choices are correct. d. wages expense
Answers: 3
You know the right answer?
1. It is said that a delay in critical path activity will delay the project, while a delay in a nonc...
Questions
question
English, 20.04.2021 03:10
question
Mathematics, 20.04.2021 03:10
question
Spanish, 20.04.2021 03:10
question
Mathematics, 20.04.2021 03:10
Questions on the website: 13722367