A manufacturing company is using a two container kanban system between a downstream and an upstream work center. Each container holds 25 parts. The using work center can handle 100 parts per day. The average elapsed time for the entire cycle is currently 0.4 days. The company is concerned about the efficiency and safety stock policy) of the operation. Required:
If the safety stock factor is changed to 0.1 and the number of parts per container is increased to 44, how many containers will be needed?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 13:30
Presented below is information for annie company for the month of march 2018. cost of goods sold $245,000 rent expense $ 36,000 freight-out 7,000 sales discounts 8,000 insurance expense 5,000 sales returns and allowances 11,000 salaries and wages expense 63,000 sales revenue 410,000 instructions prepare the income statement.
Answers: 2
question
Business, 23.06.2019 00:30
It's possible for a debt card transaction to bounce true or false
Answers: 1
question
Business, 23.06.2019 11:00
Advertisers like online advertising because
Answers: 1
question
Business, 23.06.2019 11:20
What term refers to searching for potential buyersa. follow up b. presentation c. prospecting d. approach this is on apex learning, principles of business, marketing, and financequiz 4.2.2
Answers: 1
You know the right answer?
A manufacturing company is using a two container kanban system between a downstream and an upstream...
Questions
question
Mathematics, 11.12.2019 18:31
question
Social Studies, 11.12.2019 18:31
Questions on the website: 13722362