Business, 15.12.2020 16:30 Sofianevaeh1339

A task has an optimistic completion time of 4 days, a most likely time of 10 days, and a pessimistic time of 13 days. The expected task duration is:

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 18:30
Order these statements in the correct order to fill in the central idea and key points for a chronological speech. question 22 options: there are several steps that someone must take to become a doctor. finally, you will need to get a medical license, and become board certified in your specialty area. then, you must get admitted into to medical school and earn a medical degree. next, you will need to complete a residency. first you must earn a bachelors degree.
Answers: 2
question
Business, 22.06.2019 22:50
Total marketing effort is a term used to describe the critical decision factors that affect demand: price, advertising, distribution, and product quality. define the variable x to represent total marketing effort. a typical model that is used to predict demand as a function of total marketing effort is based on the power function: d = axb suppose that a is a positive number. different model forms result from varying the constant b. sketch the graphs of this model for b = 0, b = 1, 0< b< 1, b< 0, and b> 1. (we encourage you to use excel to do this.) what does each model tell you about the relationship between demand and marketing effort? what assumptions are implied? are they reasonable? how would you go about selecting the appropriate model?
Answers: 1
question
Business, 22.06.2019 23:20
Suppose you manage an upscale restaurant in new york city. would involve writing employee schedules and a list of things to do for the chef and other kitchen staff
Answers: 3
question
Business, 23.06.2019 00:30
Greentel, a telecom giant, has been using the service of orpheus inc. for training its employees. according to a deal signed by the two companies, orpheus inc. is not only responsible for training greentel's employees but also for providing comprehensive administrative services to the telecom giant. in this instance, greentel engages in
Answers: 1
You know the right answer?
A task has an optimistic completion time of 4 days, a most likely time of 10 days, and a pessimistic...
Questions
Questions on the website: 13722363