A manufacturing receives the following order for calculators: July 5,000 units
August: 6,000 units
Setember 5,000 units

The manufacturing provided the following information for manufacturing the calculator:
Production lead time: 7 days
Quality: 5 errors per million calculators

Required:
What are the production requirements in units for the month of July?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 17:00
What are ways individuals may reduce their total education and training costs?
Answers: 3
question
Business, 21.06.2019 18:00
Abc company currently pays a dividend of $2.15 per share, d0=2.15. it is estimated that the company’s dividend will grow at a rate of 30 percent per year for the next 3 years, then the dividend will grow at a constant rate of 7 percent thereafter. the market rate of return is 9 percent. what would you estimate is the stock’s current price?
Answers: 3
question
Business, 22.06.2019 20:50
Which of the following statements regarding the southern economy at the end of the nineteenth century is accurate? the south was producing as much cotton as it had before the civil war.
Answers: 3
question
Business, 22.06.2019 21:30
Suppose that alexi and tony can sell all their street tacos for $2 each and all their cuban sandwiches for $7.25 each. if each of them worked 20 hours per week, how should they split their time between the production of street tacos and cuban sandwiches? what is their maximum joint revenue?
Answers: 3
You know the right answer?
A manufacturing receives the following order for calculators: July 5,000 units
August: 6,000...
Questions
question
Biology, 05.10.2019 21:30
question
Mathematics, 05.10.2019 21:30
Questions on the website: 13722367