A simple project listing of five activities, their predecessors and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 3 B A 2 C A 1 D B and C 3 E D 4 Using the Single Time Estimate CPM procedure, what is the Latest Finish Time for the last activity in this project (i. e., the total time to complete the project)?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 12:40
When cell phones were first entering the market, they were relatively large and reception was undependable. all cell phones were essentially the same. but as the technology developed, many competitors entered, introducing features unique to their phones. today, cell phones are only a small fraction of the size and weight of their predecessors. consumers can buy cell phones with color screens, cameras, internet access, daily planners, or voice activation (and any combination of these features). the history of the cell phone demonstrates what marketing trend?
Answers: 3
question
Business, 22.06.2019 19:20
Advertisers are usually very conscious of their audience. choose an issue of a popular magazine such as time, sports illustrated, vanity fair, rolling stone, or the like. from that issue select three advertisements to analyze. try to determine the audience being appealed to in each advertisement and analyze the appeals used to persuade buyers. how might the appeals differ is the ads were designed to persuade a different audience.
Answers: 2
question
Business, 22.06.2019 19:50
What is the present value of the following cash flow stream at a rate of 12.0%? years: 0 1 2 3 4| | | | |cfs: $0 $1,500 $3,000 $4,500 $6,000a. $9,699b. $10,210c. $10,747d. $11,284e. $11,849
Answers: 3
question
Business, 22.06.2019 20:00
If a hotel has 100 rooms, and each room takes 25 minutes to clean, how many housekeepers working 8-hour shifts does the hotel need at 50 percent occupancy?
Answers: 1
You know the right answer?
A simple project listing of five activities, their predecessors and their respective time estimates...