The longest series of connections in the project network from the start to the end of the activities is also referred to as a. the action path.
b. the critical path.
c. the master schedule.
d. float or slack.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:30
The dollar value generated over decades of customer loyalty to your company is known as brand equity. viability. sustainability. luck.
Answers: 1
question
Business, 22.06.2019 09:50
Acar manufacturer uses new machines that automatically assemble an engine from parts fed to the system. the machine can regulate the speed ofassembly depending on the number of parts produced. which type of technology does this machine use? angenoem mense wat ons in matin en esta va ser elthe machine uses
Answers: 3
question
Business, 22.06.2019 10:30
You meet that special person and get married. amazingly your spouse has exactly the same income you do 47,810. if your tax status is now married filing jointly what is your tax liability
Answers: 2
question
Business, 22.06.2019 11:30
Mark knopf is an auditor who has been asked to provide an audit and financial statement certification for a company that is going public on the new york stock exchange. knopf wants to know his personal liability if the company provides him with inaccurate or false information. which of the following sources of law will him answer that question? a. the city ordinances where the company headquarters is located. b. the state constitution of the state where the company is incorporated. c. code of federal regulations. d. all of the above
Answers: 1
You know the right answer?
The longest series of connections in the project network from the start to the end of the activities...
Questions
Questions on the website: 13722362