An electrical contractor’s records during the last five weeks indicate the number of job requests: Week: 1 2 3 4 5
Requests: 20 22 18 21 22
Predict the number of requests for week 6 using each of these methods:
a. Naive.
b. A four-period moving average.
c. Exponential smoothing with alpha= .30. Use 20 for week 2 forecast.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 10:30
Which maxim is being neglected in the following conversation? eli: how did you do at the track meet? caleb: i came in second place! eli: congratulations! what was your time? caleb: six minutes, four seconds. the guy who won only beat me by three seconds. eli: really? katie said the winning time was under 6 minutes. caleb: oh, well, he might have beat me by five seconds. a)maxim of quantity b)maxim of quality c)maxim of relevance d)maxim of manner
Answers: 1
question
Business, 22.06.2019 14:40
Which of the following statements about revision is most accurate? (a) you must compose first drafts quickly (sprint writing) and return later for editing. (b) careful writers always revise as they write. (c) revision is required for only long and complex business documents. (d) some business writers prefer to compose first drafts quickly and revise later; others prefer to revise as they go.
Answers: 3
question
Business, 22.06.2019 19:20
Although appealing to more refined tastes, art as a collectible has not always performed so profitably. during 2003, an auction house sold a sculpture at auction for a price of $10,211,500. unfortunately for the previous owner, he had purchased it in 2000 at a price of $12,177,500. what was his annual rate of return on this sculpture? (a negative answer should be indicated by a minus sign. do not round intermediate calculations and enter your answer as
Answers: 2
question
Business, 22.06.2019 21:50
Assume that (i) setups need to be completed first; (ii) a setup can only start once the batch has arrived at the resource, and (iii) all flow units of a batch need to be processed at a resource before any of the units of the batch can be moved to the next resource. process step 1 molding 2 painting 3 dressing setup time 15 min. 30 min. no setup processing time 0.25 min./unit 0.15 min./unit 0.30 min./unit which batch size would minimize inventory without decreasing the process capacity?
Answers: 1
You know the right answer?
An electrical contractor’s records during the last five weeks indicate the number of job requests:...
Questions
question
Mathematics, 31.03.2021 21:00
question
Mathematics, 31.03.2021 21:00
question
Mathematics, 31.03.2021 21:00
question
Mathematics, 31.03.2021 21:00
question
Mathematics, 31.03.2021 21:00
question
Mathematics, 31.03.2021 21:00
question
English, 31.03.2021 21:00
question
History, 31.03.2021 21:00
Questions on the website: 13722363