If the budget at completion for a project is $200,000 and the cost performance index is .5, what is the estimate at completion

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 23:00
Employees of dti, inc. worked 1,600 direct labor hours in january and 1,000 direct labor hours in february. dti expects to use 18,000 direct labor hours during the year, and expects to incur $22,500 of worker’s compensation insurance cost for the year. the cash payment for this cost will be paid in april. how much insurance premium should be allocated to products made in january and february?
Answers: 1
question
Business, 22.06.2019 03:30
Tiana daniels enterprise’s trial balance as at december 31, 2016 did not balance. on february 15, 2017 the following errors were detected: errorsi. water rates had been undercast by $2, 000.  ii. a cheque paid to yvonne walch of $2, 680 had been posted to the credit side of her account.  iii. discount received total of $1, 260 had been posted to the debit side of the discount allowed account as $1, 620.  iv. rent paid in the amount of $24, 000 had been posted to the credit of the rent received account.  v. wayne returned goods valuing $1, 680 to daniels enterprise but had been completely omitted from the books.    required: 1. prepare the journal entries to correct the errors.  (narrations required)                    14.5 marks  2.    prepare the suspense account showing clearly the original trial balance error.          8 marks
Answers: 2
question
Business, 22.06.2019 05:10
The total value of your portfolio is $10,000: $3,000 of it is invested in stock a and the remainder invested in stock b. stock a has a beta of 0.8; stock b has a beta of 1.2. the risk premium on the market portfolio is 8%; the risk-free rate is 2%. additional information on stocks a and b is provided below. return in each state state probability of state stock a stock b excellent 15% 15% 5% normal 50% 9% 7% poor 35% -15% 10% what are each stock’s expected return and the standard deviation? what are the expected return and the standard deviation of your portfolio? what is the beta of your portfolio? using capm, what is the expected return on the portfolio? given your answer above, would you buy, sell, or hold the portfolio?
Answers: 1
question
Business, 22.06.2019 09:50
For each of the following users of financial accounting information and managerial accounting information, specify whether the user would primarily use financial accounting information or managerial accounting information or both: 1. sec examiner 2. bookkeeping department 3. division controller 4. external auditor (public accounting firm) 5. loan officer at the company's bank 6. state tax agency auditor 7. board of directors 8. manager of the service department 9. wall street analyst 10. internal auditor 11. potential investors 12, current stockholders 13. reporter from the wall street journal 14. regional division managers
Answers: 1
You know the right answer?
If the budget at completion for a project is $200,000 and the cost performance index is .5, what is...
Questions
Questions on the website: 13722361