On July 1, 2020, Pearl Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Pearl estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At
12/31/20
At
12/31/21
At
12/31/22
Contract costs incurred to date $327,800 $1,180,000 $2,090,400
Estimated costs to complete the contract 1,162,200 820,000 –0–
Billings to Gumbel 300,000 1,110,000 1,870,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using either a negative sign prececeding the number e. g. -45 or parenthesis e. g. (45).)

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 15:30
Historically, 12 percent of a mail-order firm's repeat charge-account customers have an incorrect current address in the firm's computer database. the number of customers out of 19 who have an incorrect address in the database is a binomial random variable with n = 19 and 2formula36.mml = 0.12.
Answers: 2
question
Business, 22.06.2019 08:40
Calculate the cost of each capital component—in other words, the after-tax cost of debt, the cost of preferred stock (including flotation costs), and the cost of equity (ignoring flotation costs). use both the capm method and the dividend growth approach to find the cost of equity.calculate the cost of new stock using the dividend growth approach.what is the cost of new common stock based on the capm? (hint: find the difference between re and rs as determined by the dividend growth approach and then add that difference to the capm value for rs.)assuming that gao will not issue new equity and will continue to use the same target capital structure, what is the company’s wacc? e. suppose gao is evaluating three projects with the following characteristics.each project has a cost of $1 million. they will all be financed using the target mix of long-term debt, preferred stock, and common equity. the cost of the common equity for each project should be based on the beta estimated for the project. all equity will come from reinvested earnings.equity invested in project a would have a beta of 0.5 and an expected return of 9.0%.equity invested in project b would have a beta of 1.0 and an expected return of 10.0%.equity invested in project c would have a beta of 2.0 and an expected return of 11.0%.analyze the company’s situation, and explain why each project should be accepted or rejected g
Answers: 1
question
Business, 22.06.2019 09:30
What are two benefits of consumer programs
Answers: 2
question
Business, 22.06.2019 10:40
Why do you think the compensation plans differ at the two firms? in particular, why do you think kaufmann’s pays commissions to salespeople, while parkleigh does not? why does parkleigh offer employees discounts on purchases, while kaufmann’s does not?
Answers: 3
You know the right answer?
On July 1, 2020, Pearl Construction Company Inc. contracted to build an office building for Gumbel C...
Questions
Questions on the website: 13722362