You wish to build a house and you have divided the process into a number of tasks, namely: B. excavation and building the foundation,
F. raising the wooden frame,
E. electrical wiring,
P. indoor plumbing,
D. dry walls and flooring,
L. landscaping.

You estimate the following duration for each of the tasks (in weeks):

Tasks B F E P D L
Duration 3 2 3 4 1 2

Some of the tasks can only be started when some other tasks are completed. For instance, you can only build the frame once the foundation has been completed, i. e. F can only start after B is completed. All the precedence constraints are summarized as follows:

• F can start only after B is completed,
• L can start only after B is completed,
• E can start only after F is completed,
• P can start only after F is completed,
• D can start only after E is completed
• D can start only after P is completed.

The goal is to schedule the starting time of each task such that the entire project is completed as soon as possible. As an example, here is a feasible schedule with a completion time of ten weeks.

Tasks B F E P D L
Starting Time 0 3 6 5 9 6
End Time 3 5 9 9 10 8

Required:
Formulate this problem as an LP. Explain your formulation. Note that there is no limit on the number of tasks that can be done in parallel. (Hint: Introduce variables to indicate the times that the tasks start.)

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:30
Big trail running company has started to produce running apparel in addition to the trail running shoes that they have manufactured for years. they feel that a departmental overhead rate would best reflect their overall manufacturing overhead usage. based on research the following information was gathered for the upcoming year: machining department finishing department estimated manufacturing overhead by department $ 600 comma 000 $ 400 comma 000 trail running shoes 440 comma 000 machine hours 11 comma 000 direct labor hours running apparel 60 comma 000 machine hours 39 comma 000 direct labor hours manufacturing overhead is driven by machine hours for the machining department and direct labor hours for the finishing department. at the end of the year, the following information was gathered related to the production of the trail running shoes and running apparel: machining department finishing department trail running shoes 442 comma 000 hours 10 comma 500 hours running apparel 57 comma 000 hours 40 comma 000 hours how much manufacturing overhead will be allocated to the trail running shoes
Answers: 3
question
Business, 22.06.2019 00:30
Which statement is true about the elements of the interface of a presentation program? a. the status bar appears at the top of the page and displays options to style your slides. b. the tool bar displays the thumbnails of your presentation slides in the order they will appear in the presentation. c. rulers indicate the margins, tabs, and indents in a presentation slide. d. the document area provides a list of commands to create, format, and edit presentations.
Answers: 3
question
Business, 22.06.2019 19:00
20. to add body to a hearty broth, you may use a. onions. b. pasta. c. cheese. d. water.
Answers: 2
question
Business, 23.06.2019 00:00
3. which of the following occupations relate to a skill category of mathematics and data? select all that apply. (2 correct answers) engineer financial analyst mechanic sales person 4. which of the following occupations relate to a skill category of words and literacy? select all that apply. (2 correct answers) educator lawyer marketing manager psychologist architect
Answers: 1
You know the right answer?
You wish to build a house and you have divided the process into a number of tasks, namely: B. excav...
Questions
question
Mathematics, 17.05.2021 14:00
question
Chemistry, 17.05.2021 14:00
question
Business, 17.05.2021 14:00
Questions on the website: 13722360