If a worker takes 50 hours to perform a task the first time he/she does it, and the learning percentage is 80% a. How long does it take the worker to do the task the third time it is performed?
b. How long does it take the worker to do all three tasks?
c. How much longer would it take the worker to complete two additional tasks (beyond the first three)?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 11:00
Down under products, ltd., of australia has budgeted sales of its popular boomerang for the next four months as follows: unit salesapril 74,000may 85,000june 114,000july 92,000the company is now in the process of preparing a production budget for the second quarter. past experience has shown that end-of-month inventory levels must equal 10% of the following month’s unit sales. the inventory at the end of march was 7,400 units.required: prepare a production budget by month and in total, for the second quarter.
Answers: 3
question
Business, 22.06.2019 13:10
Thomas kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. thomas's fastest-moving inventory item has a demand of 6,000 units per year. the cost of each unit is $100, and the inventory carrying cost is $10 per unit per year. the average ordering cost is $30 per order. it takes about 5 days for an order to arrive, and the demand for 1 week is 120 units. (this is a corporate operation, and the are 250 working days per year.)a) what is the eoq? b) what is the average inventory if the eoq is used? c) what is the optimal number of orders per year? d) what is the optimal number of days in between any two orders? e) what is the annual cost of ordering and holding inventory? f) what is the total annual inventory cost, including cost of the 6,000 units?
Answers: 3
question
Business, 22.06.2019 21:10
This problem has been solved! see the answerthe xyz corporation is interested in possible differences in days worked by salaried employees in three departments in the financial area. a survey of 23 randomly chosen employees reveals the data shown below. because of the casual sampling methodology in this survey, the sample sizes are unequal. research question: are the mean annual attendance rates the same for employees in these three departments? days worked last year by 23 employees department days worked budgets (5 workers) 278 260 265 245 258 payables (10 workers) 205 270 220 240 255 217 266 239 240 228 pricing (8 workers) 240 258 233 256 233 242 244 249 picture click here for the excel data filefill in the missing data. (round your p-value to 4 decimal places, mean values to 1 decimal place and other answers to 2group mean n std. dev variancesbudgets payables pricing total one factor anova source ss df ms f p-value treatment error total
Answers: 2
question
Business, 23.06.2019 03:00
By changing its recipe, a smoothie chain is reacting to a change in the environment. while it is important to be able to quickly adapt, it is also important to take a proactive approach to changes in the marketing environment. implementing a proactive approach requires constantly scanning and analyzing the environment so that changes do not come as a surprise. the statements below are findings from environmental scanning and analysis. select the marketing environment force that best describes each of the statements listed.
Answers: 3
You know the right answer?
If a worker takes 50 hours to perform a task the first time he/she does it, and the learning percent...
Questions
question
History, 20.08.2020 03:01
question
History, 20.08.2020 03:01
Questions on the website: 13722361